Save Lake Lavon

Beautiful Lavon Lake, Collin County, Texas
U.S. Army Corps of Engineers Lake

 

 

Why We Oppose a Bridge Over Lake Lavon
 

Poor Communication and Coordination

Engineering disregarded previous engineering study routes:

WHY were the five proposed bridge routes, on Collin County mobility maps from 2002 to 2006, dismissed?  These routes were part of a map made by Carter Burges, which were surely paid for with tax payer money. 

Where is the record of public input that gave Collin County the idea to dismiss those routes and replace them with the new single blue line?  The single blue line became the core of the HNTB study area, yet  Mr. Delgado stated that this single blue line “was drawn without the benefit of detailed engineering” because they thought it was in the best place.


Who made the decision that this single blue line become the center of the HNTB study area?

Collin County Engineering submitted this single blue line study location to a bond vote without proper citizen input:

Collin County published two brochures prior to the vote.  One had no mention of the bridge study the other had only one line.  If this bridge study goes forward it will account for MILLIONS of dollars of Collin County bond debt.  This bridge study was worth more attention and media than a tiny one line mention in one brochure.

Decision to Start the Study and Decision to Continue the Study:

Collin County has repeatedly told us that the reason they began the Lavon Lake Bridge Study was because the citizens said they wanted it when they passed the 2007 Bond Package. 

Our surveys show that 95% of the citizens did not even know the $500,0000 for the study money was part of the bond package.  When they find out about it, they feel duped.  Those few that knew it was there thought it  had something to do with the replacement of the old Lavon Lake bridges on East Lucas Road, a worthwhile expenditure.  NONE knew that it was money that might go toward a study for a toll road.

It is clear that Collin County wants to pass the responsibility of the study expenditure to the citizens, and we accept our mistake for not watching them closely enough.  We will NOT let this happen again.  Still, we have to wonder, if citizen involvement is the answer, why did Collin County choose to continue the study after the October 7, 2009 Public Meeting.  We filled the room and clearly told them we do not want a bridge.

(FYI: The HNTB contract was written so that Collin County could have given a 30 day notice of cancellation and paid only for work completed without any other penalty, yet they would not stop the study when they found out the bridge cost was estimated at $470 million and they admitted it was too expensive and would never be built.)

Transportation Committee Issues:

The 2007 Transportation Committee was the origin of the $500,000 earmark for the Lavon Lake Bridge Study.  Commissioners each appoint members to the Transportation Committee.  At that time, Jerry Hoagland and Joe Jaynes were the Commissioners with Precincts that surrounded the lake.  They knew the citizens they appointed, so they also had to know that there was not one individual appointed to that committee that was in the area of the bridge. 

Don Dillard was appointed on this Transportation Committee this committee (page 11).  He worked for a Hunt real-estate company at this time.  He did not live in the area near the lake but Mr. Dillard had been promoting the Lavon Bridge since 2005 while working for the Hunt company.

The citizens of the lake area, not being represented, could not defend themselves from any recommendations made by Mr. Dillard or any other member of the committee.

Engineering states 100% of the citizens on the transportation sub-committee recommend this project to the Commissioner's Court.  (Page 5) We ask Collin County Engineering to show us a record of a vote that proves this to be true.  Our investigation reveals that they cannot produce a record of a vote, because there WAS NO VOTE on the subject of the Lavon Bridge Study.

Collin County Engineering has not properly coordinated their efforts:

On April 27, 2009, a district level representative of the Corps said, "I question why they chose to bisect the most boat-able parts of the lake.”  On that date, the Corps had NOT been informed of the decision to drop the five other proposed bridge routes down to one.  

On October 1, 2009, HNTB presented their feasibility route study to the USACE team. After HNTB made the presentation to the Corps, USACE expressed the Corps of Engineers current opinion on this bridge project. This is a direct quote from Mr. McLane:

"When the project Purpose and Need is defined in the NEPA document, the description would need to be "tight" for the COE to approve the project. Currently, the Purpose and Need doesn't appear to warrant COE approval for constructing a road across COE property because the road, as it is shown, is not a regional artery and feasible alternatives exist."

The bridge route connect to Parker Road that runs through a number of neighborhoods as it makes its way to Hwy 75.  A bridge or roadway that just connect city to city (local benefit only) does not meet Corps criteria.

Mr. McLane further explained that the roadway and bridge must be the ONLY feasible alternative to connect one area to the other. There are specific guidelines on this issue regarding travel time and distance. The US Army Corps of Engineers does not think any of the routes pass the Corps "only feasible alternative test."

SUMMARY:

The residents were left out when choosing a study area for the potential bridge routes. 

US Army Corps of Engineers said that Collin County engineering had been informed about the Corps guidelines but HNTB and Collin County chose locations that fail two of major guidelines.

They did not adequately inform or include all Collin County citizens prior to the bond vote.

Collin County could not have been more out of touch with the will of the citizens.  March 2009 these are the comment and sentiments given to us by Collin County;

  • There are no plans for public meetings to discuss this proposed bridge route because the bridge is such a popular plan.

  • There is no real opposition to the bridge. 

  • We never hear complaints against State Hwy 78.

  • Growth is coming and the bridge is coming.  There is nothing you can do about it.

 
What You
Can Do To Help!
Collin County
Public Meeting Notices

October 7, 2009
Public Meeting Agenda compared to
May 19, 2010 Agenda

Contact Your Government Officials:

Federal & State Officials

County Officials

City Officials

Locate Your
Elected Officials
Based on Your Address

Videos Of Past Public Meetings:

September 14th Commissioner's Meeting:
1 Toll Discussion
2 HNTB Presentation
 

October 7th Public Meeting
1  2  3  4  5  6  7  8  9

(9 Part Video)

 

 
 
 


 Please submit comments and information to:SaveLakeLavon@gmail.com